The modernization was performed successfully in 2016 within scheduled time frame. The aged LP turbine was replaced with a new footprint turbine of the same type, keeping the existing foundation and piping interfaces for minimum shutdown time. Furthermore, the outdated control system was replaced by Siemens' state-of-the-art SCAUT electronic control and protection system.
The successful completion of this project was based on the close cooperation with the customer as well as Siemens' comprehensive experience, technical expertise, and careful planning of the site activities.